Week 10: Windows and Doors 11.08.2007

Week 10: August 7th-11th

By the beginning of week 10, all of the mud blocks we were going to use to erect the walls on the Muturi home, were dry and ready to be laid. With the foundations dug, our labourers and fundis were now starting to build the sub-structure wall, and eventually pour the floor.

With our window frames in place, during week 10 we had window fitters come out to the site, and put in glass panes.

Now that the majority of the external work on the maternity ward is complete, we had to focus on the interior part of the building. We decided to tile the floor, as this was certainly the most hygienic option. Our tiler and his 6 Fundis started their work also.

With all the inside doors hung and in place, it was time for our painter and his fundis to begin sanding down the doors frames, in order for them to be varnished and eventually painted with a mahogany colour.img_5651.jpg

 

img_5656.jpg
 
 

 

 


 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

The doors to the post-natal ward are stained a mahogany colour.